Safety Induction Course Questionnaire

Ensure that all questions and safety requirements are explained in a language understood by the worker or translated by a qualified person.

Employee / Contractor Worker Particulars

Company, trade and designation can be suggested from previous forms on this device. Nationality provides country-name suggestions. Personal attendee details and signatures are not saved for suggestions.

Part #1 PPE (Personal Protective Equipment)

1
Safety helmets, safety shoes/boots, safety harnesses and ear plugs must be worn as required when entering or working on the worksite.
2
Personal Protective Equipment must be properly maintained and inspected regularly.
3
Damaged Personal Protective Equipment MUST not be used.
4
Safety glasses must be worn when carrying out grinding, cutting, hacking or any other activity that produces sparks or flying particles.
5
Welding goggles or an appropriate welding shield must be worn when carrying out welding or other applicable hot work.

Part #2 Fire Safety

1
Fire extinguishers, a fire watcher and fire blankets must be available at all times during hot work.
2
Ensure that there are no incompatible activities, combustible materials or flammable materials in the vicinity before starting hot work.
3
All welding equipment, hoses and electrical connections must be checked before starting work and again after breaks.
4
Report immediately to your supervisor if any fire extinguisher, hose or equipment is damaged.
5
In the event of a minor fire, use the nearest suitable fire extinguisher if it is safe to do so. Pull the safety pin, aim at the base of the fire, squeeze the handle and sweep from side to side. Report the incident to your immediate supervisor.
6
In the event of a major fire, move away from the fire to a safe location and alert others by shouting, "Fire! Fire! Fire!"
7
Know and follow the evacuation procedure in the event of a fire emergency.
8
Hot work may only commence after the Hot Work Permit has been approved and clearly displayed at the work area.
9
Gas cylinders must be properly secured and must not be left free-standing or unattended.
10
All requirements stated in the Hot Work Permit must be strictly complied with.

Part #3 Electrical Safety

1
Report any faulty electrical connection, tool or equipment immediately to your supervisor.
2
All electrical equipment and tools must be properly earthed where required and checked by a competent person (LEW) regularly.
3
Do not tamper with electrical connections. Ensure that all safety devices are functioning correctly.
4
Do not enter switchgear rooms, transformer rooms or substations without proper authorisation.
5
All electrical cables must be properly elevated or otherwise protected from damage.
6
Switch off electrical appliances and equipment after use.
7
All rotating cutting tools, such as hand grinders and power saws, must be fitted with the appropriate protective guards.
8
Never use tools or equipment unless you have been trained and authorised to use them.
9
Do not use binding wire or wire rope to tie or suspend electrical cables.
10
All extension connections must use approved industrial type plugs and sockets.
11
Generator sets must be properly earthed where required, provided with a suitable fire extinguisher, drip tray and shelter.

Part #4 Working at Height

1
Damaged safety harnesses must not be used.
2
When working at heights where there is a risk of falling more than 2 m, a safety harness must be worn and both safety hooks must be secured to suitable anchorage points.
3
Workers must be briefed by their supervisor before carrying out work at height.
4
All scaffolds must be erected, altered and dismantled only by competent persons.
5
Do not tamper with or modify an erected scaffold.
6
Do not move or push a mobile scaffold while any person is on it.
7
Scaffolds must have safe access to the working platform. The working platform must be fully boarded and properly arranged to prevent tripping or tipping hazards.
8
Damaged A-frame ladders with broken steps, spreaders or other defective parts must not be used.
9
Do not stand or work on the top three steps of an A-frame ladder.

Part #5 Accident / occurrences reporting procedures

1
Report all accidents, near misses, injuries, fires, and damage to company equipment or property immediately to your supervisor or safety personnel.
2
During an emergency, all personnel must proceed to the designated assembly point.

Part #6 First Aid

1
Know where to obtain first aid treatment on site (Project Office).
2
All injuries, whether minor or serious, must be treated and reported to your supervisor immediately.
3
Only trained first aiders should provide first aid treatment.

Part #7 House Keeping

1
Maintain good housekeeping daily and clean up the work area before leaving the site.
2
Keep all work areas, access routes, passageways and stairways free from obstruction.
3
Dispose of food waste in the designated food waste bins.
4
Dispose of construction waste in the designated waste bins.

Part #8 General Rules & Regulations

1
Comply with Chiu Teng Construction Pte Ltd's safety rules and regulations, as well as all applicable statutory requirements, at all times.
2
Smoking is strictly prohibited on site at all times.
3
Attendance at the daily Toolbox Meeting is compulsory before starting work.
4
Before starting any work that requires a Permit to Work, the permit application must be submitted to the safety personnel.
5
All Permits to Work must be approved by the Project Manager and clearly displayed at the work location. NO PERMIT, NO WORK.
6
All requirements and conditions stated in the relevant Permits to Work must be complied with at all times.
7
Workers will be issued with a security pass, which must be clearly displayed at all times.
8
Threatening, attempting to threaten, or using abusive words or gestures towards supervisory staff or safety personnel while they are carrying out their duties is a serious offence.
9
DO NOT OPERATE ANY MACHINERY without authorisation from the CTC Project Manager or Safety Personnel.
10
Remain within your designated work area. DO NOT LOITER around the void deck or other unauthorised areas.
11
Report any unsafe activity or condition to your supervisor immediately.
12
WHEN IN DOUBT, ASK YOUR SUPERVISOR.
13
Do not work with chemicals unless you have been properly briefed by your supervisor or safety personnel.
14
Follow all safety instructions given by your supervisor.
15
Workers are not allowed to stay overnight, cook, wash clothes or bathe on site.
16
Do not carry out any work that may endanger yourself or others.
17
Do not discharge muddy water directly into any drain.
18
Do not waste water. Ensure all water taps are turned off when not in use.

Declaration

I have fully understood and accept the contents of the Chiu Teng Construction Pte Ltd, Tanglin Halt C1 Project Safety Induction Course.

I understand and agree to comply with all safety rules and regulations of CTC, Tanglin Halt C1, as well as all applicable statutory requirements.

Accepted by

The attendee's name will be taken from the particulars above.

Translated by (if applicable)